DOES YOUR CONSTRUCTION PROJECT REQUIRE A STORMWATER PERMIT?
The term “stormwater” refers to any runoff after rain or snow from a barren piece of land, an area with vegetation, or constructed areas like paved streets and rooftops. Stormwater discharges can contain pollutants in large enough quantities to contaminate a water supply. If your construction project will disturb one or more acres of land, you might need a stormwater permit. If your project will disturb less than one acre, but its part of a larger development plan that will disturb one or more acres, you might also need a stormwater permit.
However, the determination of what the appropriate compliance is for your particular construction project is far more intricate than just a “yes” or “no” answer to the above scenarios. There are four criteria, which must be met to determine a permit is needed:
If you answered “yes” to any of the first three questions and “yes” to the last question, then you definitely need a stormwater permit. Keep in mind that in addition to state and federal regulatory agencies, some municipalities are also required to implement stormwater control programs. You need to check with your municipality for its requirements before beginning work on the project.
Your next step is determining whether to apply on the federal or state level. If your project is located in an area requiring a federal permit, you must apply for the EPA Construction General Permit (CGP). If your location necessitates getting a state permit, then you must meet the state’s general permit requirements. You can apply for an individual state or federal permit instead of the general one; however, the individual permit process can be much longer. One of the requirements of the EPA CGP is to assess the potential affects your project will have on federally protected endangered species and on any designated critical habitat on or near your site. Although state permit requirements might vary, the EPA has established some very specific criteria:
1. Develop and implement a Stormwater Pollution Prevention Plan. It has to include:
2. Submit a Notice of Intent (NOI) — This notice begins coverage under the general permit and includes a certification that the activity will not impact upon endangered species or historic places.
3. Submit a Notice of Termination (NOT) — You need to submit this to EPA within 30 days after one or more of the following: